Masonry Installation

Typical Masonry QuickTie™ Installation

Layout and mark cable locations per plan.
1
1
1

Tack Anchor Bolt Assemblies on foundation form at plan specified locations.
1
1

Pour concrete foundation.
1
1
1
1

Lay CMU first course with knockouts located at each anchor bolt (knockouts may be placed inside or outside).

Finish laying CMU block wall in running bond pattern.
1
1

Install 2X8 yellow pine wood top plates (pressure treated bottom plate) at top of CMU wall.
1

Layout each truss to ensure no conflicts with cable locations.
1
1

Drill holes in the top plates above each anchor bolt location.
1
1

Feed cables through the top plates at each anchor bolt location.
1
1

Couple each cable to the anchor bolt below.
1
1

Tension the cables to the specified load.
1
1
1

For detail installation instructions download the PDF below for your Project.

Masonry Instructions